So it's now been a week since the builders broke ground and not only do we have a hole and some footers, but now we have walls. WALLS, people! Basement walls, to be terribly specific.
Day #7 consisted of setting up the mold for the basement foundation and actually pouring the concrete into the molds. This sat over-night to cure and...
Day #8, the removed the mold and have sprayed black, water-repellent goodness on the concrete. This water-repellent protects the concrete from absorbing any water from the ground/dirt after the holes are filled around the foundation. It's preventative against any potential, future water damage. Yay for preventative maintenance! Can I get an AMEN?!
So, here's our updated schedule:
Day #1 - Monday, June 15, 2009: Ground broke and hole for basement has been dug out! Only after about 2.5 months of waiting for our building permit to come through.
Day #3 - Wednesday June 17, 2009: Footers poured and let to rest and set.
Day # 5 - Friday June 19, 2009: Mold for basement walls and foundation arrives on site.
---Day # 7 - Monday June 22, 2009: Mold is installed and concrete is poured for foundation walls. ---Day #8 - Tuesday June 23, 2009: Mold removed; black, water-repellent goodness sprayed on foundation.
Day #7
5 comments:
wow, it's going fast!!
Loved your cheer-I say give em some Eagles spirit fingers. That'll get em' moving ;)
i totally don't blame you at all for checking it out --- construction is super exciting, especially when they're moving!!
You'll be in before you know it! :)
Jess S.
Wooh-hoo!!! There be a house going up!!
Next time I need to see the in-law quarters!
Post a Comment