Day #1 - Monday, June 15, 2009: Ground broke and hole for basement has been dug out! Only after about 2.5 months of waiting for our building permit to come through.
Day #3 - Wednesday June 17, 2009: Footers poured and let to rest and set.
Day # 5 - Friday June 19, 2009: Mold for basement walls and foundation arrives on site.
Day # 7 - Monday June 22, 2009: Mold is installed and concrete is poured for foundation walls.
Day #8 - Tuesday June 23, 2009: Mold removed; black, water-repellent goodness sprayed on foundation.
Day #13 - Sunday June 28, 2009: Piping installed under house, rough-in parts for Bathroom in the basement installed.
Day #20 - Sunday July 5, 2009: Concrete is poured in Garage and Basement!! Property is leveled and sides are filled in.
Day #26 - Saturday, July 11, 2009: Lumber arrives and floor and 1st floor walls are framed and assembled.
Day #28 - Monday, July 13, 2009: Second floor added and framed.
Day #29 - Tuesday, July 14, 2009: Roof has almost been completed.